Nebius plans $40 billion 2027 spend as Microsoft site lags
Original title: Nebius tests the neocloud playbook with $40 billion in planned spending
The Vineland, New Jersey build is months late, and Microsoft can end late service after a grace period.
Nebius told investors it plans $40 billion in 2027 spending, funded largely by customer prepayments and contract-backed loans. A Microsoft-backed site in Vineland, New Jersey, run by DataOne, is months late after a switch from temporary generators to Bloom Energy fuel cells. Microsoft can terminate late service after a grace period; Nebius says Microsoft joined planning but did not say Microsoft accepted the new dates. Nebius cut its 2026 revenue forecast by $200 million to $3 billion, and shares fell 17%.
Unconfirmed: Nebius did not say Microsoft agreed to the revised dates, and Microsoft has not publicly canceled the contract.
- Only just over half of the Microsoft capacity is now due by year-end.
- The rest is planned for the second quarter of 2027.
- New Jersey regulators fined DataOne $1.1 million over unpermitted gas generators.
- Third-quarter revenue was $981 million, up 571% year over year.
- Prepayments and financing are expected to cover up to 85% of 2027 capex.
From the original article
4 min read at techcrunch.com
Nebius plans to fund its $40 billion AI infrastructure expansion through customer prepayments and loans, even as delays at a Microsoft data center raise questions about its financing model.
By Rebecca Bellan · techcrunch.com
A short excerpt; the article and its images belong to the publisher. Summary, key facts and assessment above are AI-written from the article and can be wrong.