Oracle sends force majeure notice on its New Mexico Stargate data center
Oracle issued a force majeure notice that could delay payments for its New Mexico Stargate data center.
Oracle sent a force majeure notice to the developer of Project Jupiter, a Stargate data-center campus in New Mexico, Bloomberg reported. The notice would let Oracle delay payments if the site misses its 2028 online target; sources said Oracle is not seeking to exit as the main tenant. The 2.45-gigawatt campus is designed around Bloom Energy gas fuel cells, and an Energy Transfer pipeline has been delayed nearly six months to February 1, 2027. Oracle said the project remains on schedule, and Blue Owl Capital said financial commitments are unchanged.